LIBERTAD S.A., POSADAS COMERCIAL CENTRE
Argentina


Development

- Procedure of feasibility.
- Preliminary project.
- Environmental impact study.
- Projects of infrastructure works.
- Municipal permission of works
- Media diffusion.
- Executive project and detailing: technical documentation,
documentation for bids.

Implementation

- Executive project of infrastructure works
- Management and coordination of works, infrastructure
and signage: individual system of contracts for each work
(42 contracts).
- Adjustments to the project constantly to optimize the
quality of the design, the costs and the time of work.

Works
- Hypermarket, storage rooms, trucks discharge.
- 24 commercial localities.
- Children's playroom and fast food.
- Parking for 990 cars.
- Medium-voltage tie line system (10800 ft). Station of
measurement and manoeuvre.
- Sewerage system: 7300 ft with 200 y-junctions for
residential connexions.
- Water supply system: modification of the existing water
supply line (1300 ft).
- Drainage system: construction of a concrete canal (1500
ft).
- Road system: opening (1150 ft) and paving (2400 ft).
- New access for the existing bus station.
- System of traffic lights for the adjacent avenues.